Ponderay Newsprint Company

180,000 #/hr Boiler

JLCC provided on-site inspection, installation supervision, and start-up tuning on this 180,000 #/hour propane-fired Cleaver Brooks boiler located in Washington state.

JLCC worked closely with the client and the original supply manufacturer to resolve initial design concerns, resulting in NOx levels below 30ppm throughout its operating range, with NOx levels <20ppm at lower firing rates..

Subsequent to initial installation, JLCC was on-site for follow-up tuning and consultation on air & fuel flow control issues.